Archive for October, 2009
The Grand Pier, Weston-super-Mare – going up!
26.10.09
Work has started this morning (Monday), erecting the frame of the new Pavilion building on Weston’s Grand Pier. More than 100 tonnes of steel per week will be used to form the structure of the new building. In total more than 1,100 tonnes of steel is being supplied by local firm Hayley Engineering for ….
More Information...The Grand Pier moves into constructive phase

23.10.09
After £9 million has been spent on clearing the debris, driving in piles and making good the basic structure of the Pier, visible construction has now started.
More Information...Weston on the map for trade visit

16.10.09
A record turn out of over 100 members of the UK’s largest leisure industry association representing commercial leisure parks, piers, zoos and static attractions sector visited the West Country yesterday.
More Information...Churchill School students on Grand Pier mission

12.10.09
Five A2 level product design students from Churchill School received special permission to go onto the Grand Pier building site as background for their design projects.
More Information...Grand Pier finds solution to latest weather problem

01.10.09
With force 8 gales predicted over the next few days, the first barge working on the Grand Pier will be moved today to Cardiff docks and return on Monday 5th October, weather permitting.
More Information...