Archive for January, 2010

Weather Allows Work to Continue

Weather Allows Work to Continue

19.01.10

After three weeks of waiting, the weather finally thawed last Friday and made it possible for the first concrete to be poured on the Grand Pier since the re-build started last September. Concrete was pumped from the shore along the entire length of the waist and contractors were able to create the floor of the ….

More Information...

Panoramic Tower Delay

Panoramic Tower Delay

08.01.10

The Panoramic Tower at the Grand Pier won’t be ready in time for the re-opening this summer. The deal with the original Italian suppliers fell through and despite sourcing a new supplier, delivery date guarantees were not forthcoming.

Kerry Michael said, "we have to be open as soon as possible and we are not prepared to ….

More Information...

On track for summer opening

On track for summer opening

05.01.10

The Grand Pier rebuild has progressed well over the Christmas period. The steel forming the upper floors has been installed and although not yet waterproof, most of the roof sheeting has also been installed. The general shape of the building and towers is now clearly visible.

Kerry Michael said, "The weather is quite kind to us ….

More Information...